(1) Carefully debug the conveyor after installation of each equipment to meet the drawing requirements.
(2) Each reducer, moving parts to add the corresponding lubricating oil.
(3) Install the conveyor to meet the requirements of each single equipment for manual work test, and combined to debug the conveyor to meet the requirements of the action.
(4) Debug the electrical part of the conveyor. Including the conventional electrical wiring and action debugging, so that the equipment has good performance, to achieve the design function and state.